CLIENT


Kier / SCC

 

SECTOR


Commercial Sector

 

PROJECT DURATION


8 Weeks

 

PRODUCTS USED


Klargester Bio-disc / Alton Pump service pre-packaged pump chamber

 

PROJECT TYPE


Supply and install complete with all groundworks of a sewage treatment plant.

 

LOCATION


Chertsey – In the Runnymede borough of Surrey, England.

JOB SPECIFICATION:

We identified that the clients existing sewage treatment plant was not processing and treating waste. On investigation, we found that their existing site was undersized and unable to cope with the daily flows running through it.

We were tasked with supplying and installing a new larger treatment plant that could cope with the daily water discharge/flows of the site. Once the plant had been sized we then had the task of installation. This involved the use of heavy plant machinery including the use of a crane to lift the new Klargester treatment plant into position.

We were faced with many challenges on this project including the fact that the new plant was being installed quite close to a lake which meant the groundwater table was quite high.