Alton Pumps
Pump station installation · Hampshire

Duty/standby pump station installation in Hampshire

Alton Pumps supplied the specialist pumping package, installed the twin submersible pumps and commissioned the system for a residential development in Hampshire.

Commissioned 28 February 2017 · Client identity withheld

Twin duty and standby submersible pumps installed in the Hampshire pump station wet well
The installed twin-pump wet well photographed on the commissioning date.

The project requirement

The development required a foul-water pumping station with a documented hydraulic duty and provision for reliable automatic operation. The project brief also asked for features that could support a future water-company adoption route. This case study does not claim that adoption was subsequently completed.

The recorded design duty was 5 litres per second at 4.74 metres total head, discharging through a 90 mm outside-diameter SDR11 rising main approximately 75 metres long.

Pumping equipment and controls

The supplied package used two submersible pumps in a duty/standby arrangement. Each pump had a 20-metre power cable and an 80 mm discharge connection. The GRP wet well was supplied with a co-joined valve chamber containing the discharge manifold, non-return valves and isolation valves.

A three-phase Form 2 control panel provided pump run, trip and automatic changeover functions. The level-control design included ultrasonic measurement with backup and high-level float switches. Outputs were provided for power failure, pump failure and high-level alarm telemetry interfaces.

Alton Pumps twin-pump control panel with ultrasonic level controller
Twin-pump controls and ultrasonic level controller.
Internal wiring and protection components inside the pump control panel
Internal control-panel wiring recorded during the project.

Installation and commissioning

Alton Pumps installed the pumps after completion of the civil works. The project records identify the rising main, incoming power supply and water for wet testing as supporting works provided by others.

The station was set to work and wet commissioned on 28 February 2017. Its project file contains the commissioning certificate, pump and panel test documentation, electrical records, general arrangement drawings and a dedicated operating and maintenance manual.

Recorded outcome

  • Duty/standby resilience: two submersible pumps were installed for automatic alternating operation.
  • Level and alarm control: ultrasonic control, backup floats and telemetry outputs were incorporated into the design.
  • Commissioning documented: the station was set to work, wet tested and supported by a project-specific O&M manual.