24/7 emergency pump call-out · Hampshire, Surrey, Sussex, Berkshire & London Phones answered 24/7sales@altonpumps.com
Alton Pumps
Pump chamber replacement · Havant, Hampshire

Pump chamber replacement in Havant

Alton Pumps removed an old pumping system in Havant and replaced it with a new tank, new pumps and new DN100 pipework and valves. The system was tested several times and left working in automatic.

Project completed December 2025

Two new submersible pumps with red bends and blue valves in a new pump chamber in Havant
The new pumps, bends and valves.

The agreed work

The job was to replace an existing pumping system. The agreed work included the following.

  • Remove all the old components, and remove the liquid and sludge with a waste tanker.
  • Build a two pump manifold in DN100 ductile iron, with DN100 isolation valves, gate valves and non-return valves.
  • Fit two duck foot bends on newly built plinths and connect them to the new valves.
  • Supply and install two new Grundfos pumps as specified.
  • Bring the two pipes back into one and connect to the existing discharge.
  • Supply ultrasonic controls and a GSM text alert alarm.
  • Test, commission and leave the system in full working order.
Old pumps, motors and a green tank removed from a pump chamber in Havant
The old components after removal.

Preliminary works and installation

Preliminary works were carried out on 28 October 2025. The main installation took place on 11, 12 and 15 December 2025. The old system was removed and replaced with a new tank, pumps and pipework.

Red and blue DN100 valves and bends laid out before installation
The new valves and bends laid out before installation.

Testing

The system was tested several times and was working as it should. It was left in automatic.

Completed pump chamber with two pumps, valves, a tank and a control panel on the wall
The finished chamber with pumps, valves, tank and control panel.

Ground water

The engineers noted that a lot of ground water is getting into the system. They suggested a survey to find out where it is coming from.

Recorded outcome

  • Old system removed: the old components, liquid and sludge were removed.
  • New system installed: a new tank, new pumps and new DN100 pipework and valves.
  • Tested: several times, working as it should and left in automatic.
  • Further advice: a survey was suggested to find where ground water is entering.

This case study is written from the completed job record. Photographs are from the job. Customer names and addresses are not published.

About this job

What was replaced?

The old pumping system was removed and replaced with a new tank, new pumps and new pipework and valves.

When was the work done?

Preliminary works were carried out on 28 October 2025 and the main installation took place on 11, 12 and 15 December 2025.

How was it tested?

The system was tested several times, was working as it should and was left in automatic. The engineers also suggested a survey to find where ground water is getting in.

Call now Request call-back